22nd month (April 2006)
Well, we are in the last three months before our 2 year anniversary of this project!
|
|
|
Finished the roof repair |
|
|
|
and the kid's bunk beds |
We tried several stairs |
|
Before... |
After... Now all the bin area is repaired. |
23rd month (May 2006)
In this month we should be working on the front frame!
That was the plan... But we are still waiting for the roller to bend our hollow section (frame)
We fitted the front door |
and welded the hinges in-place |
The door and hinges are from the front |
Door closed. |
|
|
The stair steps are made |
Top view |
With the stairs done, we concentrate on the floor. Starting at the rear. |
We made a hat section (pan). It is 40mm deep which will be filled with polystyrene. |
The area is completely sealed (Sikaflex). |
|
24th month (June 2006)
At the end of this month will be our 2 year anniversary.
This month we glued the floor boards down, completed the rear frame, and started on the front frame.
|
|
The roller |
|
We finished the rear frame! :-) |
|
We turned the motorhome around |
and started working on the front frame |